7/6/2018 - All code changes pertaining to the components Main Menu, Google Team Drive, Dossier, Eligibility, Audit, Application - General, Design, Coordinators and Exclusion Form must be completed and deployed to the TEST environment
- Cameron
Cameron to get the names of all 2018 applicants and their campus designations (see FT-206)
Week of 7/9/2018 - testing by ITS and bug fixes applied to the test environment
- Create
Create application in TEST to make sure of the following
- Application successfully linked to Team Drive
- Eligibility data pre-filled with the data from PS
- Campus specific sections successfully created on the Dossier
- Dossier
Dossier testing
- upload file
- create google file
- link to google file
7/10/2018
- create
create simp ticket for production deployment of the new code base
- create
create accounts in TEST for Frank, Ariana and Adam
- create
create 30 more test/prod team drives
7/16/2018 - deploy deploy new code base to production and apply schema changes
7/16/2018 - meet meet with Sandra to review exclusion changes and to prep for training on 7/18 and 7/19
7/16/2018 - create create the 2018 applications
- includes Frank and Ariana (and Adam?) from the Dept of Learning Design and Technology at Manoa
7/18/2018 - CC CC training
7/19/2018 - CC CC training
August 2018
Recommendation Page changes
...