7/6/2018 - All code changes pertaining to the components Main Menu, Google Team Drive, Dossier, Eligibility, Audit, Application - General, Design, Coordinators and Exclusion Form must be completed and deployed to the TEST environment

  • (plus)(plus) Cameron to get the names of all 2018 applicants and their campus designations (see FT-206)

Week of 7/9/2018 - testing by ITS and bug fixes applied to the test environment

  • (minus)(minus) Create application in TEST to make sure of the following
    • Application successfully linked to Team Drive
    • Eligibility data pre-filled with the data from PS
    • Campus specific sections successfully created on the Dossier
  • (minus)(minus) Dossier testing
    • upload file
    • create google file
    • link to google file

7/10/2018

  • (minus)(minus) create simp ticket for production deployment of the new code base
  • (minus)(minus) create accounts in TEST for Frank, Ariana and Adam
  • (minus)(minus) create 30 more test/prod team drives
  • (minus) verify that the setting to prevent downloading, copying and printing is set on the root of the team drive

7/16/2018 - (minus) (minus) deploy new code base to production and apply schema changes

7/16/2018 - (minus) (minus) meet with Sandra to review exclusion changes and to prep for training on 7/18 and 7/19

7/16/2018 - (minus) (minus) create the 2018 applications

  • includes Frank and Ariana (and Adam?) from the Dept of Learning Design and Technology at Manoa

7/18/2018 - (minus) (minus) CC training

7/19/2018 - (minus) (minus) CC training

August 2018

Recommendation Page changes

...